Zimbabwe Loses Legal Battle Over 17 Fire Engines Seized in Lithuania
Zimbabwe has lost a legal battle to recover 17 Belarusian fire engines that were seized and subsequently disposed of in Lithuania over international sanctions, and the Government is now exploring compensation claims and other international legal remedies.
Summary
Zimbabwe has lost a legal battle to recover 17 Belarusian fire engines that were seized and subsequently disposed of in Lithuania over international sanctions, and the Government is now exploring compensation claims and other international legal remedies. The trucks were impounded in Lithuania after sanctions were imposed on a component supplier linked to the Belarusian manufacturer. The fire engines are among 37 vehicles that the Ministry of Local Government and Public Works reported as undelivered under three procurement contracts, according to an analysis by the Parliamentary Budget Office of the ministry's 2026 first-quarter report. Zimbabwe challenged the seizure and intended disposal through the Lithuanian courts, but its appeals went as far as the highest available national legal remedies in Lithuania and failed. "Government has exhausted local remedies in Lithuania and is pursuing advice on compensation claims, international legal remedies, and contractual enforcement against the supplier," the Parliamentary Budget Office noted. The remainder of the fire engine consignment was successfully delivered through alternative routes, and the matter remains under legal and diplomatic consideration. The report does not disclose the value of the 17 fire engines or the amount the Government intends to recover.
Two more vehicle deals in dispute
The Belarusian consignment is not the only vehicle procurement deal over which the ministry is seeking legal recourse. Six years after awarding Earlgrey Motors a contract to supply 27 vehicles, the ministry is still awaiting delivery of 17 of them, with currency depreciation having weakened the financial safeguards put in place to protect public funds.
Payment was made in local currency in 2020, at a time when the country was grappling with significant inflation, exchange rate volatility and foreign currency shortages. “The supplier depended on the foreign currency auction system, where allocations were limited and not guaranteed, resulting in purported erosion of the value of funds held,” the report reads. “Although a bank guarantee had been obtained, currency depreciation reduced its effectiveness as a recovery mechanism. Seventeen vehicles remain outstanding.”
The ministry has since referred the matter to the Attorney-General for legal recovery and applied to the Procurement Regulatory Authority of Zimbabwe for the debarment of Earlgrey Motors.
Similar economic constraints frustrated another contract awarded to Sino Truck Zimbabwe in 2020 for the supply of 33 vehicles. The ministry is seeking legal advice on a possible set-off arrangement involving US$1,196,270 it owes a company affiliated with the supplier for vehicles already delivered. Most vehicles were delivered, leaving only two outstanding, although the report gives conflicting figures on the number outstanding in different sections.
A pattern the auditors have flagged
The protracted procurement disputes come against a backdrop of unresolved deficiencies in the ministry's financial and asset management systems previously flagged by the Auditor-General. Among these is a US$784,743 payment made directly by Treasury for 13 vehicles, which was not accounted for in the Public Financial Management System or the ministry's appropriation account. The ministry has also yet to finalise its risk management policy, a shortcoming the Parliamentary Budget Office warned could compromise its ability to identify and respond to risks affecting its operations.
Why this matters
Fire engines are not abstract assets: they are the difference between a fire that is contained and one that destroys a market, a school or a neighbourhood. Seventeen of them seized abroad, two more vehicle contracts still unresolved after six years, and nearly US$785,000 in payments unaccounted for in the system — together they describe a procurement system that keeps losing public money and public equipment.
Whether the compensation claims succeed will matter less than whether the ministry fixes the controls the Auditor-General keeps flagging. Until it does, the next contract is at risk of ending the same way.
Quick answers
What has Zimbabwe lost?
A legal battle to recover 17 Belarusian fire engines seized and disposed of in Lithuania over sanctions.
Why were they seized?
Sanctions were imposed on a component supplier linked to the Belarusian manufacturer.
What is the Government doing now?
Pursuing advice on compensation claims, international legal remedies and contractual enforcement against the supplier.
What else is unresolved?
Earlgrey Motors still owes 17 of 27 contracted vehicles; a Sino Truck Zimbabwe contract has two vehicles outstanding.
How much money is involved?
The report does not disclose the value of the 17 fire engines; a separate US$784,743 Treasury payment for 13 vehicles was not accounted for in the system.
What happens next?
The ministry has referred the Earlgrey matter to the Attorney-General and applied for the supplier's debarment.
Reported by
Editorial Team
Published 27 November 2026